East Norwalk Train Station Closure

The Connecticut Department of Transportation (CTDOT) is alerting customers of the upcoming temporary closure of the East Norwalk train station

  • Monday, March 11 - Sunday, March 31.
  • Work includes installing a new underdrain system under the existing East Norwalk station northern parking lot in preparation for future station improvements.
  • Train station and parking lot must be closed to accommodate construction to ensure the safety of workers. 
  • No trains will serve East Norwalk Station during this period.
  • Full regular train service remains available at the South Norwalk station and at the Westport station.
  • Free shuttle service, starting March 11.
  • East Norwalk station parking permit holders can access the South Norwalk Train Station Garage during temporary closure.
  • More information available on East Norwalk Train Station project page.

Railroad Activity 

Track and catenary work on the New Haven Line between Fort Point Street and the Strawberry Hill Avenue Railroad Bridge 

  • Monday, March 25 - Thursday, March 28, from 10:00 PM - 6:00 AM.
  • No impacts to local roads, rail service or pedestrian traffic are anticipated.
  • Noise and construction lighting are anticipated and will be monitored.

Temporary WALK Bridge closure for Metro-North Railroad (MNR) cable and track work; no bridge openings

  • Friday, March 22 - Monday, March 25.
  • No bridge openings for MNR cable removal and track-level work.
  • Schedule is subject to change.

Construction on the New Haven Line at the Fort Point StreetOsborne Avenue, and East Avenue Railroad Bridges

  • Monday, March 25 - Thursday, March 28, from 7:00 AM - 4:30 PM and 10:00 PM - 6:00 AM.
  • No impacts to local roads, rail service or pedestrian traffic are anticipated.
  • Noise and construction lighting are anticipated and will be monitored.

Marine Activity

Construction activities northeastsoutheastnorthwest and southwest of the WALK Bridge on the Norwalk River

  • Monday, March 25 - Thursday, March 28, from 7:00 AM - 4.30 PM.
  • Construction activities include pile driving for trestles, relocation of the WALK Bridge Control House and installation of secant pits ahead of micro-tunneling. 
  • Construction noise is anticipated and will be monitored. 

Other Activity

Utility work on East Avenue between Fort Point Street and the East Norwalk Train Station

  • Friday, March 22 - Thursday, March 28, from 7:00 AM - 6:00 AM.
  • No impacts to local roads, parking or pedestrian traffic are anticipated.  
  • Construction noise and lighting will be monitored.
  • Schedule is subject to change.

Road Closure on East Avenue between Fort Point Street and Winfield Street for Frontier Utility Work

  • Monday, March 11 - Sunday, March 31.
  • Road closed under the railroad bridge between Fort Point Street and Winfield Street to install new utility conduits.
  • This work is being performed by Frontier Communications and not the WALK Bridge.
  • Motorists will be detoured to Van Zant Street and Fort Point Street.
  • Schedule is subject to change.

Construction activities southwest of the WALK Bridge near North Water Street

  • Saturday, March 23, from 7:00 AM - 4:30 PM.
  • Monday, March 25 - Thursday, March 28, from 7:00 AM - 4:30 PM.
  • Activities include materials delivery, site preparation and installation of a construction access ramp to the southwest trestle.
  • Construction noise and lighting will be monitored.
  • Schedule is subject to change.

Construction activities are subject to change. Modifications to the schedule may become necessary due to weather delays or other unforeseen conditions.

El Programa de WALK Bridge ofrece servicios de traducción para todas las personas que hablan español y criollo francés. Para obtener mayor información, comuníquese con la Oficina de Información Pública del Programa enviándonos un correo electrónico a info@WALKbridgect.com o llamando al (833) 462-9255 (GO2-WALK). Adicionalmente, en la página web del Programa, WALKBridgeCT.com, ofrecemos traducciones de todos los materiales publicados a través de los servicios de Google Translate.

Pwogram WALK Bridge la ofri sèvis tradiksyon pou tout moun ki pale Panyòl ak Kreyòl Franse. Tanpri kontakte Biwo Enfòmasyon Piblik Pwogram nan pou plis enfòmasyon nan voye yon imèl ba nou nan info@WALKbridgect.com, oswa rele (833) 462-9255 (GO2-WALK). Anplis, sit wèb Pwogram nan, WALKBridgeCT.com, ofri tradiksyon pou materyèl afiche atravè sèvis Google Translate yo.